A few months ago, there was an article in the newspapers indicating that the signing of the long-awaited Host Government Agreement (HGA) between the International Oil Companies (Equinor, Shell and other partners) and the Government of Tanzania was imminent. While this is exciting news, the signing is only the initial step, and therefore it could be of value for wananchi to know what to expect post signing. It is of particular importance for stakeholders that are looking or expecting to venture into some of the opportunities that will come with the project.
The next key milestone after the signing of the HGA is the Final Investment Decision (FID) which will determine if the project is still viable from many perspectives, including economic and technical lenses, and whether it will be implemented taking into account the state of energy transition to renewable sources of energy (solar, wind, thermal) in key markets.
Progressing an LNG project from post Host Government Agreement to Final Investment Decision (FID) requires several activities to be carried out which I have analysed below in more detail:
Technical assessments
These assessments aid in defining the technical aspects of the project sufficiently, and the selection of contractors to undertake engineering, procurement and construction (EPC) works. Technical workstreams will need to complete the pre-Front End Engineering Design (Pre-FEED), Front End Engineering Design (FEED) and EPC Contract and bidding process structuring.
Pre-FEED is a contractor-led initial or preliminary designs for the intended project. The preliminary designs are informed by the initial estimates and evaluation of the size of the gas reserves, the exploitation potential, potential liquefication sites, pipelines routes and sizes. Initial cost estimates are typically based on benchmarked data from similar projects that have been done previously.
FEED, which comes after the contractor led pre-FEED, covers optimization of various plant equipment and configuration options. The basic scheme is selected for the FEED to provide better scope definition to the EPC contract bidders. Two of the key outputs from the FEED are the cost estimate and schedule projection.
EPC Contract and Bidding process structuring: Failure to implement a proper bidding process is likely to result in significant problems with project implementation. Structuring and design of the project contract and the structuring and design of the procurement process are key activities that will be carried out. By properly drafting the contract, the project sponsor will seek to achieve the following.
EPC contract bidding for a greenfield project is usually done on a competitive basis. This is essential to ensure openness and value for money which is associated with competitive bidding.
The commercial assessment
This assessment consists of securing the necessary project agreements and LNG offtake contracts. Some of the agreements that need to be finalised include:
The financial assessment
This will rely on the technical and commercial feasibility of the project to structure and secure the necessary capital investments to finance the project.
While it is possible that sponsors can finance this project under corporate finance arrangement, it is typical for the project of this size (approximated at 42 billion USD) and complexity to be financed under project finance arrangement where the project is financed purely on the strength of the projected cashflow over 30 to 40 years. Three key activities need to happen in this workstream, first is building a financial model for the project, assessment of the bankability of the project and third securing financing commitment from various finance providers i.e. financial close, which is the endgame of this workstream.
Developing a Financial Model: A comprehensive and dynamic project financial model needs to be developed. It will typically capture all the key inputs from the technical and commercial workstreams. The financial model will typically cover the entire gas exploitation period which will typically be between 30 to 40 years. The results will be subjected to different sensitivities to see the impact of different scenarios. The resulting financial metrics and ratios will be used to assess the bankability of the project.
The bankability of the projects speaks to capacity of the project company to repay its debt on the agreed schedule. Capital providers usually define some criteria to assess a project’s bankability. Some of these criteria are offtake assurance/certainty, the stability of project revenues, the ability of shareholders/sponsors to provide guarantees (especially during the construction phase), and, particularly relevant to project finance, the ratio between the cash resources generated by the project and the total amounts required to service debt. There are three most common ratios required by capital providers as indicated below:
The third aspect for this workstream is to secure commitment from financial providers which is the goal of the financial workstream.
Experienced project financiers will structure financing as blended finance, which is the use of funding from various sources, including development institutions and government, to catalyse private sector finance into the project. Some of the instruments used in blended finance include.
Final Investment Decision (FID): The final investment decision (FID) is the decision to make a final commitment to proceed with the project. This decision transitions the plan into the actual implementation of the project. Completion of the government agreements including land allocation and access. In additional to that, the project needs to have completed the financing commitments from various financiers including export credit agencies, multilateral development banks, commercial banks, and other lenders.
While much remains to be done before gas revenues can be realized the HGA is a critical first step. The subsequent activities need to be accelerated to ensure Tanzania, and its people can still benefit from the country’s gas resources before the global energy transition overtakes the appetite for fossil based and less green energy resources.